I've been testing the scheduler lately for science. No really, we do not need it in our software, I'm simply looking at its output out of curiosity.
And I noticed that an in-progress task with Suspend and Resume dates around the Data date schedules as if the suspension weren't there at all.
I assume this is a known missing feature as the Schedulers are young and full of development.